The gold band marks the target window for the Camp & CircuiTree cutover: all of Q1 2027. The actual date isn't fixed. It moves with how comfortable the Glisson team is and how much time they have to use the new system. Dashed amber segments are the workstreams built to flex if Retreats slips. The striped segment is the side-by-side run, when CircuiTree and Glisson OS are both running.
For Camp, Glisson OS and CircuiTree run next to each other. Your team can compare the two, test the new system, and build real confidence before fully relying on it. The cutover is targeted for sometime in Q1 2027. The date depends on how comfortable the Glisson team is and how much time they have to use the new system.
See how the new system handles Glisson's real camp data next to CircuiTree, side by side.
Try registration, forms, and reports in the new system while CircuiTree is still running, and check them against what you know is right.
The team learns the new system with CircuiTree still in place, so there's no leap of faith on cutover day.
Retreats falls back to a December build with an early-January launch instead of early November.
Camp & CircuiTree stays the priority. It's the highest-value module and the one your broader rollout playbook depends on proving out first. The cutover is targeted for Q1 2027, and the actual date follows how comfortable the Glisson team is and how much time they have to use the new system.
Donor CRM and Email Marketing are the workstreams that flex instead, sliding into February–March if the team's time is needed to cover the Retreats fallback and keep Camp on track in the same window.
Every workstream on the timeline above has a named owner on both sides — the pill shows which part of the roadmap they're tied to.
Glisson has no CircuiTree renewal notice window to work around.
Confirmed directly by Glisson — removes the one hard external deadline from the plan.
Glisson OS runs side by side with CircuiTree before the Camp cutover, so the team can compare and test the two before using the new system live.
It gives the Glisson team time to build confidence before fully relying on the new system.
The Camp cutover is a moving target. The target is a window covering all of Q1 2027, and the actual date depends on how comfortable the Glisson team is with the new system and how much time they have to use it.
The Glisson team decides when the new system is ready to rely on.
If Retreats slips, Camp & CircuiTree stays the priority; Donor CRM and Email Marketing absorb the schedule pressure instead.
Camp is the highest-value module and the one the broader rollout playbook depends on proving out first.
Medical Forms, Background Checks, and Digital Waivers/E-signatures are elevated ahead of Donor CRM and Email Marketing, targeted to be ready before the Camp cutover.
These are registration safety & compliance essentials, not optional add-ons.
Monthly walkthrough and training per active phase, doubling as a feedback loop into continued development.
Confirmed: any month where more than one phase is live splits into separate per-module sessions rather than one combined session.
A small, functional slice of Facilities & Site Operations moves up to November, sized to support Retreats.
Retreats needs basic facility/space management to launch; the full Facilities & Site Ops build stays targeted for March.